An activity network shows eight activities labelled A through H. The earliest start time (EST) for activity D is 11 minutes and the latest start time (LST) for activity D is 21 minutes. Activity D takes 6 minutes to complete. Calculate the float time for activity D.
General Mathematics · Unit 4 · Networks and decision mathematics 1 · Project planning and scheduling using critical path analysis (CPA)
Calculate float times for non-critical activities.
Practise this objective
AI-marked practice questions tied to QCAA mark schemes for this exact LO. Free to start.
Start free practicePractice questions for this objective
Full questions, answers and worked solutions unlock when you start a free practice session.
A construction project consists of nine activities, A to I. The project network and activity durations are shown in the diagram below. Calculate the float time for each of the following activities: (a) Activity C (1 mark) (b) Activity F (1 mark) (c) Activity H (2 marks)
The table below shows the duration, earliest start time (EST), and latest finish time (LFT) for each activity in a project. Calculate the float time for activity D.