A community theatre production requires seven activities to be completed. The table shows the activities, their duration (in days), and their immediate predecessors. Use a project network diagram with completed forward and backward scanning to determine the minimum number of days by which activity E must be shortened so that the overall project duration is reduced by 3 days.
General Mathematics · Unit 4 · Networks and decision mathematics 1 · Project planning and scheduling using critical path analysis (CPA)
Solve small-scale practical problems involving critical path analysis.
Practise this objective
AI-marked practice questions tied to QCAA mark schemes for this exact LO. Free to start.
Start free practicePractice questions for this objective
Full questions, answers and worked solutions unlock when you start a free practice session.
A construction project has the following activities: Activity A (3 days, no prerequisites), Activity B (4 days, depends on A), Activity C (2 days, depends on A), and Activity D (5 days, depends on B and C). What is the minimum project duration in days?
A building renovation project consists of five tasks with the following dependencies and durations: • Task A (4 days) must be completed before tasks B and C can start • Task B (6 days) must be completed before task E can start • Task C (5 days) must be completed before task D can start • Task D (3 days) must be completed before task E can start • Task E (2 days) is the final task What is the minimum duration of the entire project?