FeaturesHow It WorksFor ParentsPricingContactLog inStart free — no credit card needed →

General Mathematics · Unit 4 · Networks and decision mathematics 1 · Project planning and scheduling using critical path analysis (CPA)

Solve small-scale practical problems involving critical path analysis.

Practise this objective

AI-marked practice questions tied to QCAA mark schemes for this exact LO. Free to start.

Start free practice

Practice questions for this objective

Full questions, answers and worked solutions unlock when you start a free practice session.

Question 1

A community theatre production requires seven activities to be completed. The table shows the activities, their duration (in days), and their immediate predecessors. Use a project network diagram with completed forward and backward scanning to determine the minimum number of days by which activity E must be shortened so that the overall project duration is reduced by 3 days.

Worked answer
🔒 Start free to see full answer
Question 2

A construction project has the following activities: Activity A (3 days, no prerequisites), Activity B (4 days, depends on A), Activity C (2 days, depends on A), and Activity D (5 days, depends on B and C). What is the minimum project duration in days?

Worked answer
🔒 Start free to see full answer
Question 3

A building renovation project consists of five tasks with the following dependencies and durations: • Task A (4 days) must be completed before tasks B and C can start • Task B (6 days) must be completed before task E can start • Task C (5 days) must be completed before task D can start • Task D (3 days) must be completed before task E can start • Task E (2 days) is the final task What is the minimum duration of the entire project?

Worked answer
🔒 Start free to see full answer
Unlock all 3 answers — free

More in Project planning and scheduling using critical path analysis (CPA)

← Previous
Construct a project network diagram (activity on arc) to represent the durations and interdependencies of activities that must be completed during the project (excluding dummy activities).
Next →
Use ESTs and LSTs to locate the critical path/s for a project.
All LOs in Project planning and scheduling using critical path analysis (CPA)Back to full General Mathematics syllabus