A construction project consists of six activities. The table below shows each activity, its duration (in days), and its prerequisite activities. (a) Use forward scanning to determine the earliest starting time (EST) for activity F. [1 mark] (b) Use backward scanning to determine the latest starting time (LST) for activity C. [1 mark] (c) State the total project duration. [1 mark]
General Mathematics · Unit 4 · Networks and decision mathematics 1 · Project planning and scheduling using critical path analysis (CPA)
Use forward and backward scanning to determine the earliest starting time (EST) and latest starting time (LST) for each activity in the project.
Practise this objective
AI-marked practice questions tied to QCAA mark schemes for this exact LO. Free to start.
Start free practicePractice questions for this objective
Full questions, answers and worked solutions unlock when you start a free practice session.
Question 1
Worked answer
🔒 Start free to see full answer
Question 2
A community garden project involves six activities (A–F) as shown in the table below. (a) State the earliest starting time (EST) for activity E. (1 mark) (b) Use backward scanning to determine the latest starting time (LST) for activity C. (3 marks)
Worked answer
🔒 Start free to see full answer
Question 3
Activities P and Q are the critical activities for a project. What is the earliest starting time (EST) for Activity Q?
Worked answer
🔒 Start free to see full answer